Text of page 15
congressional briefings by the Congressional Research Service [13]." Note:
numbers inside parentheses refer to references in the Earthtech report #7.
In order to meaningfully tackle the subject areas outlined in the above 12
technical topics, BAASS has been compelled to focus on those projects that are
feasible given the current timelines and budget allocations for this contract. The
three sets of papers that have been submitted to the agency by MUFON,
Earthtech and by AAP Person 8
covered an enormous number of possible
directions as they sought to address the above 12 technical areas. BAASS
personnel judged it impossible logistically to embrace all of the recommendations
in these technical papers as reasonable achievables. Many of the projects could
take greater than several decades to accomplish and possibly billions of dollars.
Accordingly, BAASS has chosen eight specific projects to focus on during the
first and second years of this contract. We consider that the probability of success
of these nine projects within a 12 or 24 month time frame and within the
allocated budgets is maximized. Therefore, the objectives, methodologies,
milestones and team compositions for each of the nine projects are laid out in
detail in the next section of this Project management Report. Very recently, DIA
has mandated the creation of a ninth project, that we call Project Physics (see
page 11), in which the current research in universities and research institutes on
all twelve technical areas will be studied.
It should be stated at the outset that we deliberately adopted the stance
that the most productive way to learn the maximum about the twelve technical
areas was to study craft that are already displaying novel behavior in the twelve
technical areas. Hence, with the exception of the DIA mandated Project Physics
(see page 11) BAASS's resources will not be devoted to studying the current
"state of the art" of technology in our university system and research institutes.
This latter approach could prove fruitless and waste significant time and money.
Page 9
This information is proprietary and confidential and cannot be disseminated
or used without prior written consent from the Operating Manager of BAASS®.